▶Effective 29 Oct 2026FYI 6
Remark
New runway 01L/19R surface remark: First and last 500 feet concrete. Center 7,000 feet asphalt.
FAA text
FIRST & LAST 500 FT CONC. CNTR 7,000 FT ASPH.
Remark
New runway 01R/19L surface remark: First and last 500 feet concrete. Center 7,000 feet asphalt.
FAA text
FIRST & LAST 500 FT CONC. CNTR 7,000 FT ASPH.
Runway
Runway 01L: controlling obstacle: none listed → TREES 52 ft tall, 1056 ft from threshold, 170 ft left of centerline; obstacle clearance slope: 20:1 → 16:1
Runway
Runway 19L: controlling obstacle: none listed → TREES 80 ft tall, 2130 ft from threshold, 500 ft right of centerline; obstacle clearance slope: 34:1 → 24:1
▶Effective 03 Sep 2026IFR 3
Data: history · built 26 Nov 2026 0920Z
FAA cycle 24 Dec 2026 (upcoming) · updated . Not for navigation. Amend can be wrong, late or incomplete, and a change that isn't shown here can still be real. Always use official FAA publications, NOTAMs and a proper preflight briefing. Amend is independent and not affiliated with the FAA. Data: FAA NASR and d-TPP. How it works · Status · Changelog · Privacy · Terms · Report a problem